orissa power transmission corporation is implementing construction of 132 kv s/c line in dist. angul, orissa. construction work has been completed. the project is waiting for forest clearance. according to forest clearance sources, construction of 132 kv s/c line (2 conductors) from existing 132/33 kv grid substation at boinda to railway tracting substation at boinda. the company has applied for forest clearance for diversion of 3.94 hectares of forest land required for the project. the estimated cost of the project is rs. 57.4 million. [info as of: jun. 17]