odisha power transmission corporation is planning a substation at digapahandi, dist. ganjam, odisha. e-tenders have been invited under single stage two bid system for construction of 132kv dc line from 220/132/33kv grid substation at aska to 132/33kv grid substation at digapahandi (approximate 132 kv line length - 37.146 kms) on dc tower with construction of two nos. of 132kv feeder bay extensions each at aska & digapahandi grid substations on turnkey basis. the estimated cost of the project is rs. 227.9 million. the last date for submission online bids is 23rd may, 2017. completion period is 24 months. [info as of: apr. 17]